PILLER strengthens global presence with new production site in India

Monday, 05. May 2025

PILLER strengthens global presence with new production site in India

Piller Blowers & Compressors has taken another major step toward international growth: After just one year of construction, the new production facility at the Chordia Industrial Park in Satara, India, has been successfully completed.

New production site in India
New production site in India
New production site in India
New production site in India
New production site in India
New production site in India
New production site in India
New production site in India

With a total area of approximately 9,100 m² and an initial operating area of 2,855 m², PILLER is creating new capacity to manufacture high-quality machinery for the Asian market – built to the same quality standards as at the company's headquarters in Germany.

Christoph Böhnisch, Managing Director of Piller Blowers & Compressors GmbH, states: “Completing such a project in just twelve months is a remarkable achievement. Our heartfelt thanks go to the entire team in India and all international contributors whose outstanding dedication, drive, and team spirit made this milestone possible.”

“The goal of the new site is to shorten delivery times for regional customers, respond flexibly to market demands, and manufacture locally. Production of the VapoFan for the Indian market has already started. Beginning in 2026, the VapoFlex will also be produced – tailored to the requirements of the ASEAN region,” emphasizes Vimal Kalaria, Managing Director of Piller Global India.

A special event on the path to commissioning was the Vastu Pooja ceremony on March 30, 2025, held during the Hindu New Year festival Gudhi Padwa. Together with representatives of the global executive team and local management, the successful completion of the construction phase was celebrated as a connection between tradition and technological advancement.
 

Key Milestones at a Glance:

  • April 2024: Start of construction
  • April 2025: Completion of the production facility
  • May 2025: Start of VapoFan production
  • July 2025: Start of deliveries
     

With this new site, PILLER moves closer to customers in India and Asia – while also making a significant contribution to global sustainability goals through resource-saving, energy-efficient solutions in industrial steam processes. The new production facility complements the existing German sites and reinforces the company’s strategic focus on sustainable growth in an increasingly international market. The headquarters in Moringen remains the heart of the company.

The official inauguration of the new production facility is planned for November 2025.